Advertisements
Solution:
Statutory freeboard is = 2.0m
DW RD = 1.015 & Freeboard = 2.1m
TPC = 24, FWA = 200mm = 20cm
As we know :
Change in draft =
(Change in RD )x(FWA)
0.025
= (1.015 – 1.025 ) x 20 /0.025
= ( 0.010 x 20) /0 .025
= 8cm
Hence , actual freeboard available =( 2.1 + 0.08)m
= 2.18m
Sinkage available = ( 2.18 – 2.00)
= 0.18m
= 18cm
TPC = 24 ( Given)
24 = (A / 100) x(1.025)
A = (24 x 100)/ 1.025
A = (24 / 1.025)
= 23.414 m2
Now, TPC for RD 1.015 = (A/ 100) x(1.015)
= (23.414 x 1.015)
= 23.76 t/cm
DWT available = (sinkage x TPC)
= (18 x 23.76 )
= 427.68t.